Drama by Design were engaged by Portsmouth City Council to design and specify a new house lighting system for the Guildhall, which was supplied by Hawthorn Theatrical Ltd and installed by local contractor ICE Electrical.
The management of the venue wished to expand its range of use, particularly during the day, to include conferencing and similar events. Previous complaints that the existing house lighting was simply not bright enough had meant bringing in outside equipment and so the decision was made to install a new system. Drama by Design recommended that if installing a new system it would be sensible to move to a more efficient and sustainable system. After reviewing a number of options, GDS ArcSystem was selected, a range of LED auditorium lighting fixtures, dimmable from 0%-100% using the wireless ARC Mesh protocol.
ArcSystem was selected for its superior capacity to provide even illumination with good colour rendering and dim smoothly to any required level. As the down time available in the venue to install the system was limited, the ability to use the wireless operation to reduce the amount if wiring and therefore time required on site was a significant consideration.
In this, the largest installation of ArcSystem to date, 202 fixtures were installed, comprising 48 x Pro 4 Cell fixtures ( two of which are dual input emergency fixtures), 62 x Pro 2 Cell fixtures (10 of which are dual input emergency fixtures) and 92 x Decor 1 Cell fixtures (14 of which are dual input emergency fixtures). The system is controlled by two TX1 Master Transmitters and one six-channel control desk via GDS control software.
The hall itself provided few challenges in respect of installing the hardware apart from its size and the sheer number of fittings. Andy Stone, theatre consultant from Drama by Design was clear in his approval of ArcSystem. "The system is excellent. The products are great. They were very easy to install, with the result that we were ahead of the schedule we'd set ourselves.
"As with any project there were some teething problems, in this case associated with the wireless control, but these were down to the nature of the overall building rather than the kit and GDS were quick to help us overcome them. ArcSystem has delivered a dramatic improvement in lighting levels and will reduce maintenance and running costs, so I'd imagine the management of Portsmouth Guildhall will consider their brief well and truly met."