It's the seventh Cirque production that Summit has put into the venue. Alegria was also the first Cirque production which Summit were involved with in the central London venue, back in 1998.
The 2007 project involved the preparation of over 100 points of rigging, for which Summit has supplied 40 of their own Lodestar hoists in addition to using the house hoists.
Summit also designed and installed truss mothergrids, lighting and drape masking trusses, utilising nearly 400m of James Thomas Supertruss. This is needed for Cirque to produce their daring, highly acrobatic production in a Grade One listed venue, as opposed to staging it in their own purpose-built big top.
Before Christmas a Summit team of four riggers had worked a week of night shifts installing and proof testing anchor points, and repositioning house hoists in order to facilitate an efficient load-in, which commenced, as is now becoming a tradition, on Boxing Day.
Summit's Chris Walker then led a team of 11 riggers working split shifts over a five-day period between Christmas and New Year to ensure the show was ready for its first rehearsal on 1 January 2007.
Walker worked closely with Cirque's transfer project manager Andy Peat, RAH's consulting engineer Bob Stagg and with RAH technical show manager Simon Frost.